Taken when evaluation falls outside the special day property value.
In Selected Days
Yes
Taken when evaluation falls within the special day property value.
Node Properties
Special Day: Configures the special day settings.
For example where the 'Bank Holiday' is a substitute day then the substitute day is used rather than the actual date. e.g. if Christmas Day falls on a Saturday and the substitute bank holiday is Monday 27th December then the 'Christmas Day Bank Holiday' option will be applied on the 27th December and NOT the 25th.
The actual date 'Christmas Day (25th December)' option will be applied on the actual date of the event.
Where the option is specified as a 'Bank Holiday', the date applied will be as per the UK Government assigned Bank Holiday date for the described day ().